June Newsletter

MULLUM CREEK RESIDENTS NEWS UPDATE Construction Update The tendering process for Stage 2 construction is nearing completion and we are close to selecting a Stage 2 Contractor. As with many other current land development projects, the stretched industry has required us to carefully consider which contractors have the capacity to deliver Stage 2 in the timeframe […]

January/February Newsletter

MULLUM CREEK RESIDENTS NEWS UPDATE Construction Update The beginning of 2017 has seen a flurry of activity for the Mullum Creek development. The construction of the Stage 1 stormwater drainage outfall commenced in February and will be complete by the start of April. At the completion of these works, the installation of the extensive Stage […]

December Newsletter

MULLUM CREEK RESIDENTS NEWS UPDATE  Construction Update As the year 2016 comes to a close, there has been a lot of work done in the background so we can hit the ground running in the New Year. As soon as the festivities for the Christmas and New Year period are over, the Stage 1 civil […]

October/November Newsletter

MULLUM CREEK RESIDENTS NEWS UPDATE Construction Update The approval process of the Stage 2 design is progressing. Melbourne Water have upgraded the requirements for wetland design since our initial plans were approved, and we have had to redesign the Stage Two wetland to meet these new standards. The new design is close to completion, and […]

September Newsletter

Construction Update The Stage 2 civil design of the Mullum Creek development is more or less complete having now gone through a number of Council checks. The design of the Stage 2 wetland is being enhanced to match Melbourne Water’s new Best Practice guidelines. While this has added new layers of complexity, this will ensure […]

August Newsletter

Construction Update As we breathe a collective sigh of relief in finally gaining compliance for Stage 1 of the Mullum Creek development, our attention has quickly turned to the commencement of Stage 2. At this point in time we have a few teething issues to work through with Council, and are targeting a commencement of […]

July Newsletter

Construction Update I am pleased to report this month that we can finally expect compliance for Stage 1 within the first couple weeks of August. Negotiations with Council have concluded and bonds are being prepared in order to enable Statement of Compliance. This would mean that titles would be registered between 2-6 weeks after (depending […]

June newsletter

Construction Update Practical Completion for the Stage One internal subdivision was achieved in the middle of June, hence the actual construction activity for much of June was limited. However, we made very good gains in the administrative path to achieving Statement of Compliance, hence Settlements. Successful negotiations with Melbourne Water have led to an agreement […]

May Newsletter

Construction Update The end of a rainy May saw the completion of lot seeding, minor pavement and drainage rectifications. Despite the large rainfall, the entirety of the internal wetland infrastructure was also completed. This marked a significant milestone for Stage 1 of the subdivision and limits our exposure to future rainfall events. The final item […]

April Newsletter

Construction Update The end of April saw the end of construction for the internal subdivision. The footpaths and driveways have been completed, as well as other final miscellaneous items such as the fencing between private lots and the Council reserve. Lots and final battered areas have been levelled with appropriate topsoiling and are now ready to […]