Entries by mullum

June newsletter

Construction Update Practical Completion for the Stage One internal subdivision was achieved in the middle of June, hence the actual construction activity for much of June was limited. However, we made very good gains in the administrative path to achieving Statement of Compliance, hence Settlements. Successful negotiations with Melbourne Water have led to an agreement […]

May Newsletter

Construction Update The end of a rainy May saw the completion of lot seeding, minor pavement and drainage rectifications. Despite the large rainfall, the entirety of the internal wetland infrastructure was also completed. This marked a significant milestone for Stage 1 of the subdivision and limits our exposure to future rainfall events. The final item […]

April Newsletter

Construction Update The end of April saw the end of construction for the internal subdivision. The footpaths and driveways have been completed, as well as other final miscellaneous items such as the fencing between private lots and the Council reserve. Lots and final battered areas have been levelled with appropriate topsoiling and are now ready to […]